Determination of Resistance to Internal Pressure (TS EN ISO 1167-1)
This is one of the tests required for each batch of pipe purchases. During batch testing, PE pipes are subjected to internal pressure at 80°C for 165 hours, while PVC-U pipes are tested at 20°C for 1 hour. The pipe should complete the test duration without damage. The test pressure varies according to the material type, pipe pressure class, and test temperature.